Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News Editorials & Other Articles General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

OKIsItJustMe

(22,051 posts)
Tue May 12, 2026, 08:48 PM 11 hrs ago

xAI Adds 19 New Gas Turbines Despite Ongoing Lawsuit

https://www.wired.com/story/xai-adds-19-new-gas-turbines-despite-ongoing-lawsuit/
May 12, 2026 8:00 PM
xAI Adds 19 New Gas Turbines Despite Ongoing Lawsuit
Emails show that Elon Musk's company is expanding its use of portable gas-fired power at its Colossus 2 site as a fight over air quality continues.

xAI has added 19 natural gas turbines to its second data center campus in Southhaven, Mississippi, over the past two months, according to internal emails seen by WIRED.

The additions come as xAI is fighting a lawsuit from the NAACP and several environmental groups, alleging that the company is violating the Clean Air Act by operating more than two dozen natural gas turbines at the site without appropriate air permits.

Emails between an official in the Mississippi Department of Environmental Quality and a representative from Trinity Consultants, obtained via a public records request by the Southern Environmental Law Center and shared with WIRED, show that xAI installed 19 portable gas turbines on its site in Southaven between late March and early May. That brings the total to 46 turbines operating at the site.

A spreadsheet included in the email to MDEQ, has a column labeled “Total Power Output” that appears to list the megawatt capacity of each turbine on the site. xAI appears to have added more than 500 megawatts of natural gas turbines since mid-March.

Latest Discussions»Issue Forums»Environment & Energy»xAI Adds 19 New Gas Turbi...